Definition
Ratio of projected maintenance demand in the most loaded future window to available capacity.
The Measurement Gap
What This Metric Measures
DCI measures the degree to which AI-justified PMS deferrals are clustering into concentrated maintenance demand windows that approach or exceed dry-dock capacity, crew capacity, or class survey deadlines. It projects all currently deferred tasks forward to their new completion dates and compares the demand in the most loaded future window to that window's capacity.
The Decision It Supports
Are individually justified deferrals collectively creating a maintenance demand spike that the organization cannot absorb, and if so, how far out is the demand concentration? Each deferral is approved individually based on condition data. The question DCI answers is whether the sum of individually rational deferrals has become collectively irrational, a maintenance debt that cannot be repaid within available windows.
Why Legacy Metrics Cannot See This
PMS completion rate measures whether tasks are done on time. PMS overdue percentage counts deferred tasks. Neither metric projects the deferred tasks forward to their likely completion window and asks whether that window can absorb them. A fleet can show 95% PMS completion and zero overdue tasks (because every deferral was condition-justified and rescheduled) while building a dry-dock workload that will exceed capacity by 40%. DCI converts the snapshot of current deferrals into a forward-looking capacity projection that reveals the compounding problem before it becomes a crisis.
Formula
Primary Formula
DCI = Max_window_demand / Window_capacity
Variable Definitions
- Max_window_demand = highest projected task count in any single future maintenance window (count of deferred tasks projected to that window)
- Window_capacity = maximum task count that can be completed in that window given crew size, available duration, and facility constraints (count)
Units:
Dimensionless ratio. A value of 1.0 means the most loaded future window is exactly at capacity. Values above 1.0 mean demand exceeds capacity and some deferred tasks cannot be completed. Track alongside total deferred task count for context. Compute per vessel (dry-dock concentration) and fleet-wide (shared resource concentration).
Edge Cases
Dry-dock scheduling changes require immediate DCI recalculation. If a dry-dock is moved forward or back, the demand projection shifts. Deferred tasks with no clear future completion window are the highest-risk items and should be flagged separately as unscheduled deferrals rather than excluded from DCI. Minimum sample is all deferred tasks per vessel. A vessel with zero deferrals has a DCI of 0, which is the ideal state.
Proposed formula, pending validation pilots.