Definition
For campaigns that address a regulatory requirement, the percentage of affected assets where the campaign work order was completed within the campaign's target window: measured per-asset, not in aggregate.
The Measurement Gap
No metric tells you the per-asset completion rate of campaigns that address regulatory requirements. Disaggregated from overall campaign completion. This means AI-optimized campaign sequencing can leave the highest-risk vehicles incomplete while the aggregate completion rate looks acceptable. The gap is particularly dangerous because regulators audit compliance at the individual asset level, not the fleet average, so a 92% aggregate rate can mask a cluster of non-compliant high-exposure vehicles.
Three legacy metrics create the illusion of coverage but each has a specific blind spot:
-
Campaign completion rate reports an aggregate percentage across all assets in the campaign. This metric is blind because a 92.5% aggregate completion rate looks acceptable on a dashboard, but it conceals which specific assets remain incomplete, and whether those assets are the ones with the highest regulatory exposure or operational hours. The aggregate number cannot distinguish between missing one low-utilization spare and missing five front-line vehicles in a high-audit jurisdiction.
-
Recall Response Velocity (R-DOT-07, RRV) tracks recall-specific campaigns only, not the broader universe of regulatory campaigns such as periodic inspection mandates, emissions retrofit directives, or safety bulletin compliance. RRV is blind to any campaign that does not originate from a manufacturer recall notice, leaving a significant portion of regulatory work unmeasured.
-
Fleet maintenance completion rate blends campaign work orders with all other corrective and preventive work orders. This metric is blind because campaign-specific regulatory urgency is diluted into the overall maintenance backlog, making it impossible to isolate whether the regulatory campaign itself is on track or whether its apparent completion is an artifact of unrelated work order closures inflating the denominator.
Decision Supported:
Which specific assets in a regulatory campaign remain incomplete within the target window, and does the campaign need intervention before the compliance deadline passes?
Formula
Plain language: CRCU answers the question: of all the assets on a regulatory campaign's list, what percentage had their campaign work order completed before the campaign's target deadline? The metric is calculated per-asset so that each vehicle either passes or fails, preventing high-volume completions from masking individual non-compliance.
Notation:
$$CRCU = \frac{AssetsCompletedOnTime}{TotalCampaignAssets} \times 100$$
Variables:
| Variable | Definition | Unit |
|---|---|---|
| CRCU | Campaign Regulatory Completion Uniformity: the percentage of campaign assets completed on time | % (0–100) |
| AssetsCompletedOnTime | Count of assets where the linked campaign work order reached COMP status before the campaign's target completion date | Integer (count) |
| TotalCampaignAssets | Total number of assets on the campaign's asset list at the time of measurement | Integer (count) |
Supplemental metric:
$$CTE = \frac{\sum_{j=1}^{n} AgeDays_j}{n}$$
Campaign Tail Exposure (CTE) measures the average age in days of incomplete campaign work orders, where AgeDays_j is the number of days since the campaign target date for each of the n incomplete work orders. CTE quantifies the severity of the tail, a CRCU of 95% with a CTE of 3 days is operationally different from a CRCU of 95% with a CTE of 45 days.
Proposed formula, pending validation pilots.