Definition
The percentage of maintenance decisions that are genuinely driven by condition data from CBM/predictive systems, as opposed to silently reverting to calendar or mileage-based scheduling due to insufficient condition data.
The Measurement Gap
The organization announces a CBM program, but when the CBM engine lacks sufficient sensor data for an asset, the planner silently falls back to the calendar schedule. PM compliance against the "CBM schedule" shows 100%, but the schedule is not actually condition-based. No metric distinguishes genuine CBM-driven maintenance from calendar maintenance wearing a CBM label.
Decision Supported:
What percentage of our maintenance program is actually condition-based? When we say "we have a CBM program," how much is real CBM versus calendar maintenance with a CBM label?
Formula
Plain language: For each maintenance event, classify the trigger: was the work order generated by the CBM/predictive system based on actual condition data, or by a calendar/mileage trigger (explicitly or because the CBM system defaulted to schedule)?
Notation:
CDCR = N_cbm / N_total
Variables:
| Variable | Description | Unit |
|---|---|---|
| N_cbm | Planned maintenance WOs where the trigger was the CBM engine with condition data input | Count |
| N_total | Total planned maintenance WOs excluding emergency/breakdown | Count |
Sign Convention: Higher is better. 1.0 = all planned maintenance genuinely condition-driven.
Proposed formula, pending validation pilots.