Definition
OVPLT pairs Obsolescence Velocity, the rate at which a part's procurability is decaying, with Prediction Lead Time, how far ahead of the vendor's official end-of-life notice the system detected the decay.
The Measurement Gap
Standard item-status tracking (Active → Pending Obsolescence → Obsolete) is reactive. The status changes after the vendor's end-of-life notice arrives, by which point you are already in last-time-buy mode. Inventory Turns says nothing about future replenishability. OTIF measures delivery against promises, not the vendor's willingness to keep making promises. Reorder-point calculations assume stable supply and cannot represent lead time trending toward infinity. Fill Rate is retrospective. None of these metrics model the trajectory of procurability: they measure supply chain performance in steady state, but obsolescence is by definition the slow death of a supply line.
Decision Supported:
When to initiate engineering change orders, last-time-buy decisions, AM qualification investments, or alternate-source qualification. While there is still time to act.
Formula
Plain language: Compute a composite procurability score from supplier-count trend, lead-time trajectory, and order-fill reliability; take its negative time derivative as Obsolescence Velocity. Prediction Lead Time is the gap (in days) between when your system first flagged the decline and when the vendor formally announced end-of-life.
Notation:
OV_i = −ΔP_proc,i / Δt
PLT_i = t_vendor_EOL − t_system_flag
Portfolio OV Risk = Σ_i (OV_i × C_replacement,i)
Variables:
| Variable | Definition | Unit |
|---|---|---|
| P_proc,i | Normalized procurability score for item i (supplier count + lead time + fill reliability) | 0–1 |
| Δt | Measurement period (quarterly) | Years |
| OV_i | Obsolescence velocity for item i | Score / year |
| t_vendor_EOL | Date of official vendor end-of-life notification | Date |
| t_system_flag | Date the system first flagged high-OV status | Date |
| C_replacement,i | Estimated replacement cost including engineering-change cost | $ |
Proposed formula, pending validation pilots.